Connection inquiries and grid capacity
Please note that determining the connection feasibility also requires checking the transmission possibilities of the transmission system operator, Fingrid Oyj, which may affect the processing time and the realization of the connection. Additionally, EPV Alueverkko performs its own simulation regarding the connection’s effects on its electricity network, and a decision on the potential realization of the connection will be made based on these results.
EPV Alueverkko Capacity Map Service
In the EPV Alueverkko capacity map service, you can view the national location and technical data of the company’s networks. The map service can be utilized, for example, when preparing new connection inquiries.
The map includes details such as:
- Location of substations and power lines
- Substation type
- Status (whether the substation or power line is in use)
- Available consumption and production capacity (MW)
The map service can be opened in a new browser window here.