Connection inquiries and grid capacity

Connecting to the EPV Alueverkko network

Your connection inquiry should include the following information:

  • Project developer
  • The line or substation to which the project is intended to be connected. If this is unknown, please include a map of the area.
  • Whether it is a production or consumption facility
  • Capacity requirement (MW)
  • Project timeline: when is the planned start date and when would the project be complete?

We aim to respond to inquiries within approximately one month.

Please note that investigating the connection also requires checking the transmission possibilities with the national grid company Fingrid Oyj, which may affect the processing time. Additionally, EPV Alueverkko will perform its own grid simulation to assess the impacts of the connection.

 

Privacy Overview
EPA

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

Analytics

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.